16th St Resurfacing & Culvert Replacement Project


This project will consist of resurfacing approximately 2 miles of 16th Street from Lane Avenue (Near Menard’s) to Kollen Park Drive.  Project will also include replacement of a large diameter culvert and some watermain under 16th Street located just east of Lincoln Avenue.

Work on this project will begin Monday, June 15th with Phase 1 between Kollen Park Drive and River Avenue.

This project will be done in Three (3) phases -
Phase 1 - Kollen Park Dr - River Ave; June 15 - mid-July
     Paving is being completed on Phase 1 July 14.  VanRaalte @ 16th St will be closed traffic until July 15 to allow asphalt to cool.      Pavement markings will be applied July 15.  Phase 1 will be reopened to traffic upon completion of paving and pavement      
     markings.

Phase 2 - River Ave - Lincoln Ave; mid-July to September
     Work will transition to Phase 2 on July 16.  During the 1st portion of this phase only 16th St between River & Central will be
     closed to traffic.  The intersections of River & Central will remain open for north/south traffic.
 
Phase 3 - Lincoln Ave to Lane Ave; September to late October

The Contractor for this job is Kamminga & Roodvoets, Inc (K & R).
Jeff Talsma, Project Manager 616.949.0800 ext. 130
Aric Thorne, City Project Engineer 616.928.2444